It’s been a long and hot summer here in Southwest Florida, but thanks to our dedicated on-site crew and equally-dedicated contractors, encouraging progress continues on the renewal of Sanibel Arms West. Here are the highlights as we continue to look forward:
- 10 of 13 Condominium Roofs are now restored, with the final 3 well into the process of restoration! Given the sunny days and high temperatures, it’s not been an easy task — but our roofing contractor and their teams have certainly tackled with enthusiasm!
- Almost All Unit Interiors Have Been Framed In and feature state-of-the-industry steel interior framing!
- Electrical, Plumbing and HVAC Progress is Still Underway across the property, with most units also fully equipped with new hurricane glass windows and sliders!
- Another Sign of Progress: the Sanibel Arms West Rental Office has been reroofed, electricity is restored and a new interior will soon be completed.